Change Impact Assessment Example: An ERP Implementation
This change impact assessment example shows what a completed assessment can look like for an ERP implementation across affected Roles and Teams.
The fictional example below follows a mid-sized company replacing several disconnected purchasing and accounts-payable practices with an integrated ERP procure-to-pay process.
For the full methodology behind planning, conducting, validating, and analyzing an assessment, see how to do a Change Impact Assessment.
ERP Implementation Scenario
The Business Change
The company is implementing a standardized ERP procure-to-pay process across its U.S. operations.
Current State
- Purchase requests use inconsistent forms and email.
- Managers approve purchases outside the purchasing system.
- Supplier data is maintained in several local files.
- Accounts Payable manually resolves many invoice exceptions.
- Finance reporting depends heavily on spreadsheet consolidation.
Future State
- Purchase requests begin and remain in the ERP workflow.
- Approval limits and routing are enforced in the system.
- Supplier information follows centralized data standards.
- Automated matching isolates invoices that require intervention.
- ERP dashboards provide shared financial and purchasing information.
Completed Change Impact Assessment Example
Each record below describes a distinct impact experienced by a Role or Team. The table uses a practical subset of the fields maintained in the Change Adaptive assessment template.
| Impact ID | Role / Team | Impact Type | Description | Impact Timing | Severity | Business Criticality | Priority Score | Notes |
|---|---|---|---|---|---|---|---|---|
| 001 | Accounts Payable Analysts | Process / Workflow | Resolve unmatched invoice exceptions directly in a new ERP exception queue instead of routing them through email and supervisor review. | When Change Takes Effect | 4 | 5 | 20 | High-volume exception types include price, quantity, and receipt mismatches. |
| 002 | Accounts Payable Analysts | Role / Responsibility | Shift from routine invoice matching toward monitoring automated matches and investigating exceptions that require judgment. | When Change Takes Effect | 4 | 5 | 20 | Supervisor escalation remains available for exceptions outside analyst authority. |
| 003 | Procurement Specialists | Data / Information | Use centralized supplier and item records governed by common data standards instead of maintaining local reference files. | Before Change Takes Effect | 4 | 4 | 16 | Supplier and item data are currently maintained differently across business units. |
| 004 | Department Managers | Decision / Approval | Approve purchases through system-routed workflows using defined approval thresholds instead of replying to email requests. | When Change Takes Effect | 3 | 4 | 12 | Approval thresholds vary by management level and purchase value. |
| 005 | Purchase Requesters | System / Technology | Enter required accounting and purchasing information in the ERP request form before a purchase can enter the approval process. | When Change Takes Effect | 2 | 5 | 10 | Required accounting and purchasing fields must be complete before workflow routing begins. |
| 006 | Finance Managers | Reporting / Analytics | Use ERP dashboards and standardized reports instead of consolidating weekly purchasing and payment information in spreadsheets. | Early Post-Change | 3 | 4 | 12 | Finance teams currently use different spreadsheet definitions for several purchasing measures. |
| 007 | Procurement Specialists | Process / Workflow | Initiate purchase orders through the standardized ERP sourcing workflow rather than using locally managed purchasing steps. | When Change Takes Effect | 4 | 3 | 12 | Some local sourcing exceptions fall outside the standard purchasing workflow. |
| 008 | Site Managers | Policy / Procedure | Stop approving purchases after commitment and follow the new requirement that approval must occur before an order is placed. | Before Change Takes Effect | 3 | 4 | 12 | After-the-fact approvals occur most often at selected operating sites. |
| 009 | Purchase Requesters | Process / Workflow | Check request status in the ERP rather than contacting Procurement or Finance for routine progress updates. | When Change Takes Effect | 2 | 2 | 4 | ERP status visibility replaces routine email inquiries about request progress. |
| 010 | ERP Support Team | Role / Responsibility | Provide first-line support for procure-to-pay workflow issues and distinguish user, data, configuration, and integration problems. | During Transition | 4 | 4 | 16 | The support model covers cutover and stabilization, with escalation for configuration and integration issues. |
Priority Score equals Severity × Business Criticality. The score helps compare impacts, but it should be interpreted with the Role or Team, description, timing, and other assessment information.
Why the Change Impact Ratings Differ
Severity reflects how substantial the change is for the affected group. Business Criticality reflects the importance of the work being affected. Three records from the ERP example show why the ratings do not always move together.
What the ERP Assessment Reveals
Looking across the records identifies patterns that are difficult to see when each impact is considered separately.
Accounts Payable has the most consequential impacts
Accounts Payable faces substantial changes to responsibilities and exception handling around highly critical financial work. This shows why impact count alone can be misleading when deciding where attention is most needed.
Most of the significant change is not purely technical
The stronger impacts involve workflow, responsibility, data standards, decision rights, and procedures rather than system navigation alone.
Several groups change behavior at the same time
Many impacts are classified as When Change Takes Effect, while the ERP Support Team is already under pressure During Transition. The timing pattern shows where preparation and support need to be coordinated across groups.
How the CIA Findings Translate Into Action
The appropriate response depends on the nature, priority, and timing of the impact.
Accounts Payable
Provide hands-on exception scenarios, clarify decision authority, confirm procedures, and prepare targeted support for the period when the new process takes effect.
Procurement
Prepare specialists for both the standardized purchasing workflow and centralized data standards, including how exceptions will be handled.
Managers
Reinforce approval authority and the requirement to use the ERP workflow before purchases are committed.
Purchase Requesters
Provide concise guidance on required request information and where to check status in the new workflow.
ERP Support
Prepare support staff to distinguish user, workflow, data, configuration, and integration issues during the transition period.
Using This Change Impact Assessment Example for Your Project
The specific impacts and ratings will differ from project to project. What should remain consistent is the level of specificity: identify a distinct change for a particular Role or Team, rate Severity and Business Criticality separately, record when the impact occurs, and capture enough context to support later planning.
If you are preparing for interviews, workshops, or working sessions to identify impacts, the Change Impact Assessment question bank provides prompts for exploring changes to processes, roles, technology, data, decisions, workload, behavior, and other aspects of work.
Build Your Own Change Impact Assessment
Change Adaptive’s Change Impact Assessment templates give you the structure and analysis tools to build your own assessment from the impacts you identify.
View Change Impact Assessment TemplatesChange Impact Assessment Example FAQ
How many impacts should a Change Impact Assessment include?
There is no fixed number. The assessment should capture the distinct impacts needed to understand what is changing for affected Roles and Teams. A large project may contain many more impacts than the 10 records shown in this simplified ERP example.
Can the same Role or Team have multiple change impacts?
Yes. A Role or Team may experience several different changes to its workflow, responsibilities, technology, data, decisions, or other aspects of work. When those changes need to be understood or rated separately, they should be captured as separate impact records.
Does a Change Impact Assessment need to be completed all at once?
No. A Change Impact Assessment can be refined as the project becomes clearer. New impacts may be identified, descriptions may become more specific, and ratings may change as project decisions are finalized and additional information becomes available.
Is a Change Impact Assessment the same as an ERP impact assessment?
An ERP impact assessment can be a Change Impact Assessment when it focuses on how the implementation changes the work experienced by affected Roles and Teams. The same approach can also be used for restructures, process changes, operating-model changes, policy changes, and other organizational changes.